HUTHut 8 Corp.
Industry Bitcoin miner AI pivot Updated 26 Sep 2026 Price 23 Oct 2026
If management hits its targets, one share in 12 months
$61.23 → $61.23
Promises vs. what happened
15 claims · 8 decksEvery target management put in a slide deck, and whether they hit it, missed it, or quietly dropped it.
| Promise | Made in | What happened | |
|---|---|---|---|
| 9.3 EH/s at ~20 J/TH by Q1 '25 | Q3 '24 | 9.3 EH/s on time | Held |
| Vega energised Q2 '25 | Q4 '24 | energised on time | Held |
| American Bitcoin lists early Sep '25 | Q2 '25 | listed on time | Held |
| River Bend built with little capital at risk | Q1 '25 | 2% spent before the lease | Held |
| Build it non-recourse and non-dilutive | Q1 '26 | $7.5bn raised that way | Held |
| ~24 EH/s of self-mining by Q2 '25 | Q3 '24 | 26.8 EH/s, a quarter late, inside ABTC | Late |
| 1,530 MW into development, four sites | Q3 '25 | 1,300 MW leased; two sites unnamed since | Late |
| Vega at ~$400K per MW | Q1 '25 | never reported again | Dropped |
| $250M buyback, Dec '24 | Q4 '24 | not one share bought | Dropped |
| IESO capacity contracts from May '26 | Q2 '25 | plants sold three months before | Dropped |
| ~25% yield on cost from hosting ABTC | Q2 '25 | eliminated in consolidation; never shown | Dropped |
| A path to an investment-grade rating | Q4 '25 | the notes are rated, the parent is not | Open |
| $1.1B of annual NOI, raised to $1.75B+ | Q1 '26 | none received yet | Open |
| Beacon Point Q3 '27 and Q2 '28 | Q2 '26 | open; $9-11M per MW | Open |
| $135M a year from BITMAIN colocation | Q3 '24 | $1.2m; its own subsidiary bought the machines | Missed |
What they’re pitching
the headline page, deck by deckThe headline from each quarterly results deck over two years, so you can see what they want you to focus on, and when it changes.
'24Q4
'24Q1
'25Q2
'25Q3
'25Q4
'25Q1
'26Q2
'26
ResultsOff page one Q3 '25
Power firstPage one since Q2 '26
PipelineOff page one Q4 '25
MiningFirst seen Q3 '24
ABTCFirst seen Q1 '25
CampusesOff page one Q2 '26
Lease valueFirst seen Q1 '26
CapitalFirst seen Q4 '24
BitcoinFirst seen Q4 '24
on the headline page further in the deck not in the deck▲ onto page one▼ off page one● first mentionTap a mark for the quote.
Financial highlights up front
“Financial and operating highlights”
Deck Hut 8 Q3 2024 Earnings Call Presentation · p. 3 ·
Financial highlights up front
“Full year results”
Deck Hut 8 Q4 and Full Year 2024 Earnings Call Presentation · p. 12 ·
Financial highlights up front
“Present: Q1 2025 drivers and key metrics”
Deck Hut 8 Q1 2025 Earnings Call Presentation · p. 9 ·
Financial highlights up front
“Theme 1: Impact of first-quarter investments”
Deck Hut 8 Q2 2025 Earnings Call Presentation · p. 4 ·
Financial highlights up front
“Q3 2025 financial highlights”
Deck Hut 8 Q3 2025 Earnings Call Presentation · p. 5 ·
Financial highlights up front
“Full-year 2025 financial highlights”
Deck Hut 8 Q4 and Full Year 2025 Earnings Call Presentation · p. 8 ·
Financial highlights up front
“Q1 2026 financial highlights”
Deck Hut 8 Q1 2026 Earnings Call Presentation · p. 9 ·
Financial highlights up front
“Q2 2026 financial highlights”
Deck Hut 8 Q2 2026 Earnings Call Presentation · p. 13 ·
Power first
“Building a next-generation energy infrastructure platform”
Deck Hut 8 Q3 2024 Earnings Call Presentation · p. 6 ·
Power first
“We believe the value of energy will continue to rise as the technologies fueling both daily life and world-changing innovation place ever-greater demands on a constrained electrical grid”
Deck Hut 8 Q4 and Full Year 2024 Earnings Call Presentation · p. 3 ·
Power first
“Validation of our power-first strategy”
Deck Hut 8 Q3 2025 Earnings Call Presentation · p. 6 ·
Power first
“Power First: Hut 8 acquires, develops, and commercializes power toward its highest-value use at any point in time”
Deck Hut 8 Q2 2026 Earnings Call Presentation · p. 5 ·
Development flywheel and power pipeline
“Development pipeline update 5.0+ GW 3.0+ GW”
Deck Hut 8 Q3 2024 Earnings Call Presentation · p. 5 ·
Development flywheel and power pipeline
“Develop: Building a high-velocity, utility-scale power origination pipeline 3”
Deck Hut 8 Q4 and Full Year 2024 Earnings Call Presentation · p. 8 ·
Development flywheel and power pipeline
“Maintain the scope and velocity of our power origination pipeline”
Deck Hut 8 Q1 2025 Earnings Call Presentation · p. 6 ·
Development flywheel and power pipeline
“Theme 3: Executing at scale through our development flywheel”
Deck Hut 8 Q2 2025 Earnings Call Presentation · p. 6 ·
Development flywheel and power pipeline
“Acceleration of our development flywheel”
Deck Hut 8 Q3 2025 Earnings Call Presentation · p. 4 ·
Development flywheel and power pipeline
“Our development platform: Nearly 10 GW of energy capacity”
Deck Hut 8 Q4 and Full Year 2025 Earnings Call Presentation · p. 6 ·
Development flywheel and power pipeline
“Our development platform: 9+ GW of energy capacity”
Deck Hut 8 Q1 2026 Earnings Call Presentation · p. 7 ·
Development flywheel and power pipeline
“Hut 8 manages its development pipeline as an underwriting discipline focused on conversion”
Deck Hut 8 Q2 2026 Earnings Call Presentation · p. 10 ·
Bitcoin mining fleet upgrade
“PRO FORMA SELF-MINING HASHRATE AND BREAKEVEN ENERGY COST 5.6 EH/s”
Deck Hut 8 Q3 2024 Earnings Call Presentation · p. 7 ·
Bitcoin mining fleet upgrade
“EXECUTED FLEET UPGRADE”
Deck Hut 8 Q1 2025 Earnings Call Presentation · p. 8 ·
American Bitcoin carve-out
“Future: Strategic impact of American Bitcoin The launch of American Bitcoin marks a pivotal shift in our platform trajectory, accelerating our transition to power and digital infrastructure 1 2 3 4”
Deck Hut 8 Q1 2025 Earnings Call Presentation · p. 11 ·
American Bitcoin carve-out
“American Bitcoin advances toward Nasdaq listing”
Deck Hut 8 Q2 2025 Earnings Call Presentation · p. 7 ·
American Bitcoin carve-out
“Reporting structure: American Bitcoin accounting treatment”
Deck Hut 8 Q3 2025 Earnings Call Presentation · p. 11 ·
American Bitcoin carve-out
“Began shifting the business away from a cyclical capex growth model through the launch and public listing of American Bitcoin Began the process of lowering our cost of capital by migrating away from volatile revenue streams toward more predictable cash flows”
Deck Hut 8 Q4 and Full Year 2025 Earnings Call Presentation · p. 12 ·
AI data-center campuses (River Bend, Beacon Point)
“Our power-first strategy in action:”
Deck Hut 8 Q4 and Full Year 2024 Earnings Call Presentation · p. 19 ·
AI data-center campuses (River Bend, Beacon Point)
“Having secured 592 acres of land, initial sitework is now underway”
Deck Hut 8 Q1 2025 Earnings Call Presentation · p. 12 ·
AI data-center campuses (River Bend, Beacon Point)
“Development update: River Bend”
Deck Hut 8 Q2 2025 Earnings Call Presentation · p. 16 ·
AI data-center campuses (River Bend, Beacon Point)
“Launch of a multi-site 1.5 GW+ expansion program”
Deck Hut 8 Q3 2025 Earnings Call Presentation · p. 7 ·
AI data-center campuses (River Bend, Beacon Point)
“River Bend data center: Preliminary rendering”
Deck Hut 8 Q4 and Full Year 2025 Earnings Call Presentation · p. 5 ·
AI data-center campuses (River Bend, Beacon Point)
“Beacon Point data center: Preliminary rendering”
Deck Hut 8 Q1 2026 Earnings Call Presentation · p. 5 ·
AI data-center campuses (River Bend, Beacon Point)
“Beacon Point is fully commercialized under two 352 MW IT leases, each on substantially the same terms, with $19.6B in total base-term value”
Deck Hut 8 Q2 2026 Earnings Call Presentation · p. 7 ·
Contracted lease value
“Hut 8 has secured $16.8B of contracted lease value to date”
Deck Hut 8 Q1 2026 Earnings Call Presentation · p. 6 ·
Contracted lease value
“Hut 8 has secured $26.6B of contracted lease value to date”
Deck Hut 8 Q2 2026 Earnings Call Presentation · p. 8 ·
Capital strategy
“Fortify: Building a capital strategy that supports balanced, risk-adjusted growth 2”
Deck Hut 8 Q4 and Full Year 2024 Earnings Call Presentation · p. 7 ·
Capital strategy
“Capital planning and investment priorities Key priorities”
Deck Hut 8 Q1 2025 Earnings Call Presentation · p. 21 ·
Capital strategy
“Capital strategy update: Key initiatives”
Deck Hut 8 Q2 2025 Earnings Call Presentation · p. 15 ·
Capital strategy
“Our fortress balance sheet is a foundation for balanced, risk-adjusted growth”
Deck Hut 8 Q3 2025 Earnings Call Presentation · p. 15 ·
Capital strategy
“FY 2025 in Review 01 Protect shareholder value through disciplined use of equity capital 02 Minimize enterprise risk 03 Diversify liquidity sources by tapping new pockets of capital, including in the private markets 04 Maintain a strong balance sheet that affords strategic flexibility and a path toward ultimately achieving an investment-grade rating”
Deck Hut 8 Q4 and Full Year 2025 Earnings Call Presentation · p. 12 ·
Capital strategy
“Bitcoin held outside collateral covenants by ~3,300 BTC 01 Maintain strong parent-level liquidity 02 Pursue non-recourse, non-dilutive financing 03 Continued progress toward investment-grade rating”
Deck Hut 8 Q1 2026 Earnings Call Presentation · p. 13 ·
Capital strategy
“Capital structure: Project-level capital preserves parent-level flexibility”
Deck Hut 8 Q2 2026 Earnings Call Presentation · p. 17 ·
Strategic Bitcoin reserve
“Strategic Bitcoin reserve growth”
Deck Hut 8 Q4 and Full Year 2024 Earnings Call Presentation · p. 7 ·
Strategic Bitcoin reserve
“Execute from strong liquidity position 10,264 Bitcoin held in reserve, valued at $847.2 million as of March 31, 2025, available to be deployed into high-growth projects”
Deck Hut 8 Q1 2025 Earnings Call Presentation · p. 21 ·
Strategic Bitcoin reserve
“Generating value from Bitcoin as a treasury reserve asset”
Deck Hut 8 Q2 2025 Earnings Call Presentation · p. 15 ·
Strategic Bitcoin reserve
“Leverage 13,696 Bitcoin in reservewith a market value of approximately $1.6 billionas of September 30, 2025, of which 10,278 were held by Hut 8 and 3,418 were held by American Bitcoin Addition of a $200 million revolving credit facility with Two Prime”
Deck Hut 8 Q3 2025 Earnings Call Presentation · p. 15 ·
Strategic Bitcoin reserve
“$1.3 billion in cash and Bitcoin holdings as of quarter-end”
Deck Hut 8 Q1 2026 Earnings Call Presentation · p. 13 ·
What they keep talking about · 11
The themes that show up deck after deck, and the ones that disappear.
- Results
- In all eight, and it led two of them. From Q3 '25 it sits behind the business update, and gross margin joins it in Q4 '25.
- Power first
- The Q4 '24 "our conviction" opener, back in Q3 '25 as "validation of our power-first strategy", and by Q2 '26 the opening slide: a track record from Bravo in 2022 to Beacon Point in 2026.
- Pipeline
- In every deck, and shrinking: 5.0+ GW, then ~12.3, 10.8, 8.65, 8.5, ~8.4, ~8.7 GW. Two stages were added along the way and the exclusivity test was loosened in Q2 '26.
- Mining
- Last shown in Q1 '25. The hashrate and fleet-efficiency slide left the deck when mining moved into American Bitcoin.
- ABTC
- Most of the Q1 '25 deck, then the listing in Q2 '25, then the accounting treatment in Q3 '25. By Q1 '26 it is a line in the segment commentary and its revenue is eliminated.
- Campuses
- A power map in Q4 '24, a rendering leading Q4 '25 and Q1 '26, and in Q2 '26 two 352 MW leases with $19.6bn of base-term value. The decks never name the tenant.
- Lease value
- New in Q1 '26: $16.8bn, then $26.6bn. Each figure is paired with an upside case that assumes every renewal option is exercised — $42.8bn, then $67.9bn.
- Capital
- Bitcoin-backed credit and at-market programmes in 2024-25, ring-fenced project notes in 2026, and "no recourse debt at the parent level" by Q2 '26.
- Bitcoin
- A reserve to show off until Q3 '25 (13,696 BTC, $1.6bn). Q1 '26 gives only cash and bitcoin together; Q2 '26 gives no reserve figure at all.
- New
- Q2 '26: $1.86M of NOI per IT megawatt, $9-11M of construction cost per megawatt, 1.42 PUE and dated deliveries — the first time the economics of a lease are in the deck.
- Quiet
- The bitcoin count, the energy cost per MWh and the hashrate all stopped, and adjusted EBITDA was redefined in the quarter that made the prior year's headline figure 98% smaller.
Every quarterly report we’ve saved · 8
The press releases and shareholder letters behind this page.
- Q2 2026 release · 8-K 4 Aug 2026
- Q1 2026 release · 8-K 6 May 2026
- Q4 2025 release · 8-K 25 Feb 2026
- Q3 2025 release · 8-K 4 Nov 2025
- Q2 2025 release · 8-K 7 Aug 2025
- Q1 2025 release · 8-K 8 May 2025
- Q4 2024 release · 8-K 3 Mar 2025
- Q3 2024 release · 8-K 13 Nov 2024
Archived as text; the links open the copies filed on EDGAR or the investor-relations site.
What analysts asked them
6 calls · Q3 24 – Q2 26The last eight earnings calls: what analysts kept asking about, which questions got dodged, and how much the CEO did the talking.
Share of questions by topic, call by call. A topic that suddenly dominates is usually the problem. The last row is how much of the answering the CEO did, rather than the CFO or others.
| Share of questions about… | Q3 24 | Q4 24 | Q1 25 | Q2 25 | Q1 26 | Q2 26 |
|---|---|---|---|---|---|---|
| Demand & customers | 17% | 48% | 18% | 29% | 50% | 36% |
| Growth & sales | 25% | 9% | · | 12% | 17% | 9% |
| Pricing & margins | 25% | 4% | 9% | 18% | 6% | 18% |
| Guidance & outlook | · | · | 5% | · | · | · |
| Capacity & supply | 50% | 22% | 23% | 29% | 33% | 45% |
| Capital & financing | 25% | 22% | 9% | 24% | 6% | 36% |
| Competition | · | 9% | 9% | 6% | 11% | · |
| Products & technology | · | 13% | 9% | · | 6% | · |
| Macro & regulation | · | · | 5% | 6% | 6% | · |
| Other | 33% | 39% | 45% | 24% | 22% | 18% |
| Questions | 12 | 23 | 22 | 17 | 18 | 11 |
| How much the CEO talked | 91% | 94% | 98% | 100% | 99% | 73% |
Who’s in charge, who’s selling
read from the filings · 1 Oct 2026Shareholder votes against the board and pay, plus which executives have been selling their own shares.
Tier 1 · worsening
$361m of pay to two executives, and 45% of the votes against it
The chief executive's 2025 total compensation was $239,909,042 against $10,280,140 in 2024, and the chief strategy officer's $121,221,587 — 2,423 times the median employee. Most of it is the one-time Transformation Awards of 2 November 2025: four-year performance units, half on market-capitalisation growth and half on the appreciation of the stake in American Bitcoin, plus time-based units for the chief executive alone. Say-on-pay drew 45.2% against in June 2026, up from 1.2%.
Tier 2 · stable
Half the pay keys off a subsidiary with no pay committee that the same two men run
American Bitcoin is 53.6% owned, carries 94.9% of first-half revenue, runs its own at-market programme and pushes 46.37% of its losses to the minority. The proxy states it "does not maintain a compensation committee", and Hut 8's chief executive is its executive chairman while Hut 8's chief strategy officer is its chief executive. Half of the Transformation Awards vests on that stake's appreciation. The other half pays on market capitalisation, which also rises when a company sells stock.
Tier 2 · stable
$7.5bn of project notes against one start-up tenant, in buildings that do not exist yet
Debt was $7.74bn at 30 June 2026 against $234m of unrestricted cash and $6.79bn of restricted. River Bend's whole 245 MW is let to Fluidstack, whose rent services $3.25bn of notes, backstopped by Google; the chief executive named Anthropic as the end user. No leased capacity had been delivered, the first delivery is targeted for Q3 2027, and quarterly adjusted EBITDA is $10.4m.
Tier 2 · worsening
The number a deck led with was later restated by 98%
Adjusted EBITDA was redefined in Q2 2026 to exclude gains and losses on digital assets: Q2 2025, the figure that quarter's deck led with, falls from $221.2m to $4.2m. The stock pay added back rose from $3.8m to $51.2m over the same eight quarters. Three measures were dropped — energy cost per MWh, self-mining hashrate and the bitcoin reserve count — and the "exclusivity" pipeline stage was loosened to site control plus a power study.
Tier 3 · stable
Auditor changed in 2025, with no disagreement, and two directors sold outright
KPMG replaced Raymond Chabot Grant Thornton on 25 March 2025 with no disagreement and no reportable event, and was ratified with 1.8% against. Over the year to June 2026, insiders sold $13.1m across 16 sales with no purchases and 11% under plans; two of the five sellers are independent directors selling outright, one of them the chair of the governance committee.
Where shareholders voted no
At each annual meeting shareholders vote on who sits on the board, what the executives are paid and whether the company may create more shares. These are the votes that drew the most "no"s at the last two meetings: the shares voted against (or withheld) each year, then what share of all votes cast that was. Under each one, what the vote was about and what a no means.
| 2025 | 2026 | Share 2026 | |
|---|---|---|---|
| Say on pay (advisory)Executive pay. Shareholders say whether they accept what the top executives were paid. The vote is advisory: the board can ignore it, but a large no is a public rebuke and boards usually change the pay plan after one. | 0.6M | 32.0M | 45.2% |
| Amend the incentive planStock to pay staff and executives. Lets the company create new shares to hand out as pay. Every new share makes each existing share a slightly smaller slice of the company, so a no says shareholders think the dilution is too much. | 2.9M | 10.7M | 15.2% |
| Shattuck (pay committee chair)A board seat. Shareholders vote to keep this person on the board, the group that hires, pays and can fire the CEO. A no, or a withheld vote, says they want this director out, often because of the committee they sit on or a decision they signed off. | 1.4M | 7.4M | 10.4% |
| Wilkinson (governance chair)A board seat. | 7.5M | 5.5M | 8.1% |
| Genoot (chief executive)A board seat. | 0.2M | 0.3M | 0.4% |
Insiders who sold the most stock
Reported sales by executives and directors, biggest first.
| Form 4s, Jul '25-Jun '26 | Sold | Note |
|---|---|---|
| Rickertsen, director | $3.65M | 33,987 shares at $105 and $110 in May '26, both outright |
| Wilkinson, governance chair | $2.0M | 20,000 shares at $100.78 on 21 May '26 |
| Semah, chief legal officer | $1.25M | 10,000 shares at $125.00 on 17 Jun '26, his third sale of the year |
| All insiders | $13.1M | 16 sales by 5 people, 11% under a plan, and not one purchase |