Industry Power nuclear Updated 28 Sep 2026 Price 23 Oct 2026
If management hits its targets, one share by the end of 2029
Held at $26.35
Promises vs. what happened
14 claims · 8 decksEvery target management put in a slide deck, and whether they hit it, missed it, or quietly dropped it.
The dates slip and the cost guides only go up. Ground was broken on time; every licensing date was replaced by a new route, and isotope revenue has moved three times.
| Promise | Made in | What happened | |
|---|---|---|---|
| INL site work from Q3 '25 | Q2 '25 | ground broken Sep '25 | Held |
| Blasting from mid-Nov '25 | Q3 '25 | under way by Q4 '25 | Held |
| 2024 cash use $35-45M, loss $40-50M | Q3 '24 | cash $38.4M; loss $52.8M | Late |
| Groves critical by 4 Jul '26 | Q3 '25 | 5 Aug '26, a month late | Late |
| First NRC licence application, more in 2025 | Q3 '24 | none filed; route moved to DOE | Dropped |
| INL running late '27 or early '28 | Q1 '25 | date dropped; the CFO now says 2028 | Dropped |
| 14 GW pipeline, 12 GW from Switch | Q4 '24 | figure withdrawn after Q2 '25 | Dropped |
| Ohio's first 150 MW around 2030 | Q4 '25 | open; not repeated in 2026 decks | Open |
| Tennessee recycling, early 2030s | Q3 '25 | open; still pre-application | Open |
| Centrus fuel from 2029 | Q2 '26 | open; a letter of intent | Open |
| FY25 cash use $65-80M | Q1 '25 | $82.2M | Missed |
| INL licence Phase I, early Q4 '25 | Q2 '25 | replaced by DOE authorization | Missed |
| Isotope revenue by Q1 '26 | Q4 '24 | moved three times; none yet | Missed |
| Isotope reactor licence filed in 2025 | Q1 '25 | not filed; gone from the decks | Missed |
What they’re pitching
the headline page, deck by deckThe headline from each quarterly results deck over two years, so you can see what they want you to focus on, and when it changes.
'24Q4
'24Q1
'25Q2
'25Q3
'25Q4
'25Q1
'26Q2
'26
PolicyPage one since Q2 '26
PipelineOff page one Q2 '26
NRC licenceFirst seen Q3 '24
DOE routeOff page one Q2 '26
Aurora-INLOff page one Q2 '26
FuelFirst seen Q3 '24
IsotopesOff page one Q2 '26
ModelOff page one Q4 '25
on the headline page further in the deck not in the deck▲ onto page one▼ off page one● first mentionTap a mark for the quote.
Policy tailwinds
“The nuclear sector is experiencing unprecedented tailwinds driven largely by A.I. power needs 4”
Deck Third Quarter 2024 — Presentation · p. 4 ·
Policy tailwinds
“The new administration is making nuclear power a priority for American energy abundance 4”
Deck Fourth Quarter 2024 — Presentation · p. 4 ·
Policy tailwinds
“Growing political support for nuclear deployment”
Deck First Quarter 2025 — Presentation · p. 3 ·
Policy tailwinds
“Executive Orders on nuclear energy 3”
Deck Second Quarter 2025 — Presentation · p. 3 ·
Policy tailwinds
“2024 & 2025 marked a crucial shift in U.S. nuclear policy 4”
Deck Fourth Quarter 2025 — Presentation · p. 4 ·
Policy tailwinds
“U.S. nuclear tailwinds are shifting from policy support to execution”
Deck First Quarter 2026 — Presentation · p. 4 ·
Policy tailwinds
“U.S. policy is expanding execution capabilities across the nuclear value chain.”
Deck Second Quarter 2026 — Presentation · p. 3 ·
Customer pipeline in megawatts
“Oklo customer pipeline & PPA strategy 16”
Deck Third Quarter 2024 — Presentation · p. 16 ·
Customer pipeline in megawatts
“Oklo’s customer pipeline has grown significantly in the last 18 months primarily due to A.I. data center demand 22”
Deck Fourth Quarter 2024 — Presentation · p. 22 ·
Customer pipeline in megawatts
“Oklo's scalable technology is well suited to customers across a broad range of segments, including data centers, demonstrated by a 14 GW demand pipeline.”
Deck First Quarter 2025 — Presentation · p. 21 ·
Customer pipeline in megawatts
“Scalable product offering validated by a 14 GW pipeline, with customers across data center, utility, oil and gas, and industrial sectors”
Deck Second Quarter 2025 — Presentation · p. 23 ·
Customer pipeline in megawatts
“Scalable product offering validated by a robust pipeline, with customers across data center, utility, oil and gas, and industrial sectors”
Deck Third Quarter 2025 — Presentation · p. 19 ·
Customer pipeline in megawatts
“Built customer pipeline across data centers, industrials, energy, and government customers”
Deck First Quarter 2026 — Presentation · p. 3 ·
NRC combined licence (COLA) strategy
“Plan to submit first 15MW combined license application”
Deck Third Quarter 2024 — Presentation · p. 10 ·
NRC combined licence (COLA) strategy
“INL Powerhouse: NRC licensing developments 11”
Deck Fourth Quarter 2024 — Presentation · p. 11 ·
NRC combined licence (COLA) strategy
“Oklo initiated Phase 1 of its pre-application readiness assessment for the Aurora-INL Powerhouse COLA with the NRC.”
Deck First Quarter 2025 — Presentation · p. 11 ·
NRC combined licence (COLA) strategy
“Targeting submission for Phase I of Aurora-INL's COLA early Q4 2025”
Deck Second Quarter 2025 — Presentation · p. 11 ·
NRC combined licence (COLA) strategy
“NRC COLA timeline update”
Deck Third Quarter 2025 — Presentation · p. 4 ·
DOE authorization and Reactor Pilot Program
“Oklo is shifting Aurora-INL to pursue DOE authorization to accelerate its timeline to initial operations.”
Deck Third Quarter 2025 — Presentation · p. 6 ·
DOE authorization and Reactor Pilot Program
“Oklo is pursuing DOE authorization for initial assets, to inform NRC licensing for subsequent assets”
Deck Fourth Quarter 2025 — Presentation · p. 25 ·
DOE authorization and Reactor Pilot Program
“Advanced site work, procurement, and DOE authorization for Aurora-INL”
Deck First Quarter 2026 — Presentation · p. 3 ·
DOE authorization and Reactor Pilot Program
“Aurora-INL PDSA approval advances final design and construction.”
Deck Second Quarter 2026 — Presentation · p. 14 ·
Aurora-INL build
“Progress on Oklo’s path to its first”
Deck First Quarter 2025 — Presentation · p. 10 ·
Aurora-INL build
“Kiewit selected as lead constructor for the Aurora-INL”
Deck Second Quarter 2025 — Presentation · p. 17 ·
Aurora-INL build
“Oklo breaks ground on the Aurora-INL”
Deck Third Quarter 2025 — Presentation · p. 8 ·
Aurora-INL build
“Broke ground on the Aurora Powerhouse at INL”
Deck Fourth Quarter 2025 — Presentation · p. 3 ·
Aurora-INL build
“Broke ground on the first Aurora powerhouse at Idaho National Laboratory”
Deck First Quarter 2026 — Presentation · p. 3 ·
Aurora-INL build
“Construction, procurement, and system integration advancing”
Deck Second Quarter 2026 — Presentation · p. 14 ·
Fuel strategy and HALEU supply
“Oklo received DOE approval for Aurora fuel fabrication conceptual safety design report 14”
Deck Third Quarter 2024 — Presentation · p. 14 ·
Fuel strategy and HALEU supply
“Oklo has one of the most comprehensive fuel strategy of any advanced nuclear company”
Deck First Quarter 2025 — Presentation · p. 12 ·
Fuel strategy and HALEU supply
“Understanding HALEU supply, cost, and market dynamics 13”
Deck Second Quarter 2025 — Presentation · p. 13 ·
Fuel strategy and HALEU supply
“Oklo's fuel strategy solving near-, mid-, and long-term demand 12”
Deck Third Quarter 2025 — Presentation · p. 12 ·
Fuel strategy and HALEU supply
“Oklo’s multi-source fuel strategy”
Deck Fourth Quarter 2025 — Presentation · p. 17 ·
Fuel strategy and HALEU supply
“A3F — Advancing fuel fabrication readiness 11”
Deck First Quarter 2026 — Presentation · p. 11 ·
Fuel strategy and HALEU supply
“Oklo’s fuel strategy reduces reliance on any single pathway.”
Deck Second Quarter 2026 — Presentation · p. 18 ·
Isotopes (Atomic Alchemy, Groves)
“Oklo signs term sheet to acquire Atomic Alchemy 17”
Deck Third Quarter 2024 — Presentation · p. 17 ·
Isotopes (Atomic Alchemy, Groves)
“Completion of Atomic Alchemy acquisition enhances Oklo’s industry leading nuclear technology platform 24”
Deck Fourth Quarter 2024 — Presentation · p. 24 ·
Isotopes (Atomic Alchemy, Groves)
“Atomic Alchemy's two project strategy for entering the radioisotope market”
Deck First Quarter 2025 — Presentation · p. 17 ·
Isotopes (Atomic Alchemy, Groves)
“Atomic Alchemy targets first operations by July 2026 10”
Deck Third Quarter 2025 — Presentation · p. 10 ·
Isotopes (Atomic Alchemy, Groves)
“Completed the acquisition of Atomic Alchemy and is significantly through construction at our Groves facility in Texas, our first radioisotope test reactor • Completed fast-spectrum plutonium criticality experiments, supporting validation of plutonium fuel use in Oklo reactors”
Deck Fourth Quarter 2025 — Presentation · p. 3 ·
Isotopes (Atomic Alchemy, Groves)
“Acquired Atomic Alchemy and built the Groves test reactor facility in 229 days”
Deck First Quarter 2026 — Presentation · p. 3 ·
Isotopes (Atomic Alchemy, Groves)
“Groves achieved first criticality in under one year.”
Deck Second Quarter 2026 — Presentation · p. 10 ·
Business model framing
“Attractive Build, Own, Operate Business Model”
Deck Third Quarter 2024 — Presentation · p. 7 ·
Business model framing
“Oklo’s three competitive advantages will enable the deployment of powerhouses at scale”
Deck Second Quarter 2025 — Presentation · p. 9 ·
Business model framing
“Oklo’s competitive advantages should enable the deployment of powerhouses at scale”
Deck Third Quarter 2025 — Presentation · p. 3 ·
Business model framing
“Oklo’s three integrated business units create a scalable, vertically integrated nuclear platform 5”
Deck Fourth Quarter 2025 — Presentation · p. 5 ·
Business model framing
“Oklo is building an integrated platform where Power is the anchor, Fuel is the enabler, and Isotopes expand high-value product and service opportunities 6”
Deck First Quarter 2026 — Presentation · p. 6 ·
Business model framing
“Oklo’s three business lines reinforce delivery of one scalable, vertically integrated nuclear platform.”
Deck Second Quarter 2026 — Presentation · p. 4 ·
What they keep talking about · 10
The themes that show up deck after deck, and the ones that disappear.
- Policy
- The opening slide in five of eight decks: AI power demand in 2024, executive orders in 2025, DOE programmes in 2026.
- Pipeline
- 0.7, 2.1, then 14 GW after the Switch agreement; from Q3 '25 a robust pipeline with no number, and no binding contract in any deck.
- NRC licence
- The licence-application plan led the 2024 decks; it is last mentioned in Q3 '25, when Aurora-INL moved to DOE authorization.
- DOE route
- New in Q3 '25 with the Reactor Pilot Program; by Q2 '26 the preliminary safety analysis is approved, with no date on the next steps.
- Aurora-INL
- Kiewit in Q2 '25, groundbreaking in Q3 '25, on the highlights page in Q4 '25 and Q1 '26; never a cost.
- Fuel
- In seven of eight decks: the 5 t DOE award first, then plutonium, the Tennessee recycling centre and the Centrus letter of intent.
- Isotopes
- The commercial isotope reactor led until Q3 '25; from Q4 '25 the Groves test reactor carries the story, and its criticality leads Q2 '26.
- Model
- Build, own, operate (selling power, not plants) through Q3 '25; a Power, Fuel and Isotopes platform from Q4 '25.
- New
- Q1 '26: capex and investing cash flow ($126.9M in H1 '26). Q2 '26: Groves first criticality and the Centrus HALEU letter of intent.
- Quiet
- The 14 GW pipeline after Q2 '25, the full-year burn outlook and the progress checklist after Q3 '25, and the late-2027 operations date after Q2 '25.
Every quarterly report we’ve saved · 3
The press releases and shareholder letters behind this page.
- FY2024 letter · 8-K 24 Mar 2025
- Q3 2024 letter · 8-K 14 Nov 2024
- Q2 2024 letter · 8-K 13 Aug 2024
Archived as text; the links open the copies filed on EDGAR or the investor-relations site.
What analysts asked them
8 calls · Q3 24 – Q2 26The last eight earnings calls: what analysts kept asking about, which questions got dodged, and how much the CEO did the talking.
Share of questions by topic, call by call. A topic that suddenly dominates is usually the problem. The last row is how much of the answering the CEO did, rather than the CFO or others.
| Share of questions about… | Q3 24 | Q4 24 | Q1 25 | Q2 25 | Q3 25 | Q4 25 | Q1 26 | Q2 26 |
|---|---|---|---|---|---|---|---|---|
| Demand & customers | 23% | 36% | 12% | 50% | 17% | 21% | · | 16% |
| Growth & sales | 5% | 9% | 4% | 8% | 8% | · | · | 11% |
| Pricing & margins | 9% | · | 8% | · | · | · | · | 11% |
| Guidance & outlook | · | · | 4% | · | 8% | 29% | · | 5% |
| Capacity & supply | 9% | 45% | 38% | 50% | 67% | 29% | 57% | 26% |
| Capital & financing | 9% | 9% | 12% | 8% | 8% | 29% | 14% | 21% |
| Competition | 9% | · | · | · | · | · | · | 5% |
| Products & technology | 5% | · | · | · | 8% | 7% | 14% | 21% |
| Macro & regulation | · | 9% | 12% | 17% | 8% | 14% | 14% | 11% |
| Other | 59% | 36% | 50% | 33% | 25% | 21% | 29% | 32% |
| Questions | 22 | 11 | 24 | 12 | 12 | 14 | 7 | 19 |
| How much the CEO talked | 93% | 96% | 92% | 97% | 92% | 87% | 89% | 81% |
Who’s in charge, who’s selling
read from the filings · 7 Oct 2026Shareholder votes against the board and pay, plus which executives have been selling their own shares.
Tier 1 · live
The share count grew 15% in one half, and the ATMs keep being refilled
160.5m shares at 31 Dec '25, 185.1m at 30 Jun '26. A $1.5bn programme finished in Q1 '26 at $96.95 net a share; a $1bn one sold out by 10 Sep at falling prices; a new $1bn one opened the next day. The equity plan adds 5% of the shares to its pool every January to 2034.
Tier 2 · worsening
The founders sold $222.6m in a year; no insider bought
The DeWittes sold 3.02m shares from Nov '25 to Sep '26, $190.2m of it under plans and $69.2m on 22 Dec '25 alone. The CFO sold $21.4m. On 13 Mar '26 the founders and the CFO sold $11.4m at $60.00, off-plan, four days before the FY2025 results.
Tier 2 · stable
The CEO is chairman and his wife is COO, behind a staggered board
Chairman since Altman left in April 2025. Eight of eleven directors are independent and a lead independent director was named in April 2026, with four nuclear and industry directors; terms are three years in three classes, elected by plurality.
Tier 2 · stable
Pay is time-vested and discretionary, and holders get no vote on it
CEO $7.04m for 2025, CFO $5.87m; every executive award vests on service alone and bonuses are at the board's discretion. As an emerging growth company Oklo holds no say-on-pay vote.
Tier 3 · stable
A director's firm on a $1m-a-year retainer; the 2024 weakness is fixed
Michael Klein's firm advises Oklo for $250,000 a quarter (12.2% withheld from him in 2025). A 2024 control weakness was remediated in 2025; there is no auditor opinion on controls while Oklo is an emerging growth company.
Where shareholders voted no
At each annual meeting shareholders vote on who sits on the board, what the executives are paid and whether the company may create more shares. These are the votes that drew the most "no"s at the last two meetings: the shares voted against (or withheld) each year, then what share of all votes cast that was. Under each one, what the vote was about and what a no means.
| 2025 | 2026 | Share 2026 | |
|---|---|---|---|
| Kinzley (audit chair)A board seat. Shareholders vote to keep this person on the board, the group that hires, pays and can fire the CEO. A no, or a withheld vote, says they want this director out, often because of the committee they sit on or a decision they signed off. | — | 11.8M | 16.7% |
| Klein (director, paid adviser)A board seat. | 5.4M | — | — |
| Caroline DeWitte (COO)A board seat. | — | 0.3M | 0.5% |
| Deloitte (auditor)The auditor. Keeping the outside accounting firm that checks the company's books. This almost always passes; a sizeable no means shareholders doubt the audit or think the firm has been in place too long. | 0.4M | 0.4M | 0.3% |
Insiders who sold the most stock
Reported sales by executives and directors, biggest first.
| Form 4s, Oct '25-Sep '26 | Sold | Note |
|---|---|---|
| The DeWittes, founders (joint) | $222.6M | 3.02m shares; $69.2m on 22 Dec '25 |
| Bealmear, CFO | $21.4M | every month; $4.3m off-plan on 13 Mar '26 |
| Goodwin, chief legal officer | $3.6M | seven sales, none under a plan |
| All insiders | $249.3M | ten sellers, 80% under plans, not one purchase |